November 12, 2026
The chain-link at Henry Schmidt Park now wraps most of the grounds. Since Oct. 26 it has also covered the four tennis courts and the basketball courts, which are being resurfaced on a schedule that runs to Dec. 11, 2026. The recreation building is still open, and so are the large field and the meadow. Behind the fence, crews are building an inclusive playground with a Train Depot theme, along with new play and sand areas, shade, picnic spots, pathways and fitness stations.
Henry Schmidt is one of several park projects underway at the same time in Santa Clara this winter. A state grant deadline is a big part of why it's under construction now, while Maywood Park is still waiting for its design to begin.
In 2020, Santa Clara applied for state Proposition 68 park money to rebuild the Maywood Park playground. Maywood's rehab is now years away from construction, and that grant has to be spent by June 30, 2028. At the Sept. 15 meeting, the City Council voted to move $256,622 of it from Maywood to Henry Schmidt, as San José Spotlight reported. The California Department of Parks and Recreation still has to approve the change.
Parks & Recreation Director Damon Sparacino told the outlet that Henry Schmidt "is further along in the project delivery process and is anticipated to be completed before the Proposition 68 grant deadline of June 30, 2028." He added that the grant requires a local match, and "the Henry Schmidt Park project has sufficient Measure I (funds) to meet the grant's matching requirements."
Measure I is the 30-year, $400 million infrastructure bond that Santa Clara voters approved in 2024. San José Spotlight also reported that the city faces a roughly $624 million infrastructure deficit, and more than $200 million of it falls outside what Measure I will cover. With bond money spread that thin, grant timing becomes the tiebreaker. A project that can show progress before a state deadline moves up the line, and one still waiting on design moves back.
Under the proposed change, Maywood wouldn't lose any money. The city would replace the $256,622 with the same amount of Measure I money. Maywood's plan has also grown since the original application. It now covers playground accessibility and safety upgrades, sports court work, ADA improvements, a walking loop, lighting and a shade structure. The estimated cost is now more than $5 million, up from the roughly $2 million in the 2020 grant application.
The same logic of starting whatever is ready has put several projects under construction at the same time. Here's where they stand going into the holidays, based on the city's project pages:
| Park or facility | What's being built | Closed now | Still open | City's target |
|---|---|---|---|---|
| Henry Schmidt Park | Train Depot-themed inclusive playground, fitness stations, paths, parking lot, lighting | Most of the park; tennis and basketball courts through Dec. 11 | Recreation building, large field and meadow | Playground in spring 2027 |
| Bowers Park | Parking lot rebuild with solar canopy, EV chargers, bioretention area | Cabrillo Avenue parking lot | Pedestrian access | Spring 2027 |
| Central Park, Phase 2 | New entrance and traffic signal at Kiely Blvd. and Kaiser Drive | Work zone at the entrance | Magical Bridge Playground, basketball courts, Creek Trail access | Summer 2027 |
| George F. Haines International Swim Center | Rehab of three pools, new dive tower, mechanical building, outdoor showers | Entire facility, since January 2024 | None | Phase 1 in mid-to-late 2027 |
Henry Schmidt construction started on Feb. 2, 2026, and was planned to take about 14 months. Crews work weekdays from 7 a.m. to 5 p.m. and take city holidays off. While the courts there are closed, the city suggests using other Santa Clara tennis and basketball facilities.
The Bowers project began Aug. 31. Losing the Cabrillo Avenue lot mostly affects people who drive in, since you can still walk into the park.
The swim center has been closed the longest. It shut in January 2024, and the city held the Phase 1 groundbreaking on May 12, 2026.
Central Park, at 909 Kiely Blvd., is the one spot where the construction schedule runs into the holiday calendar.
The entrance, accessibility and parking project there was split into two phases. Phase 1 closed the Pavilion parking lot, the Pavilion picnic area and its bathrooms, and the children's playground. During that phase, the Arbor picnic area could only be reached from the Kiely Boulevard side, neither picnic area could be reserved, and the restrooms near the Lawn Bowl facility stayed open. In its Sept. 10 City Hall News bulletin, the city said Phase 1 was expected to wrap up by the end of September and that the Pavilion lot would reopen once that work was done.
Phase 2 covers the new entrance and signal at Kiely Boulevard and Kaiser Drive and is expected to run until summer 2027. During this phase, Magical Bridge Playground, the basketball courts and the Creek Trail pedestrian access stay open. The city points visitors to the CRC lot or to the Pavilion lot "once reopened."
The city's Holiday Tree Lighting is at Central Park on Friday, Dec. 4, from 5:30 to 8 p.m. The event page lists Santa photos, a holiday stage, a market, crafts, food and treats, and booths from city departments and sponsors. Santa photo tickets are free and first-come, first-served, with photo times from 6 to 8 p.m. For parking, the page lists:
Before you drive over, check the Central Park project page to see whether the Pavilion lot is open. Patricia Drive and the library drop-off don't depend on the construction schedule. The tree lighting page is where the city posts updated event details.
Three dates are left on the city's holiday calendar:
Because the two Dec. 4 events overlap by 30 minutes, you can catch Santa photos at Central Park early in the evening and still make it to the Mission for most of the Festival of Lights.
Maywood Park on Pruneridge Avenue is still open as it is. Its playground and tennis courts work, and its restrooms are open. The city says the Maywood project hasn't been canceled, is funded in the 2026-27 and 2027-28 capital improvement budgets, and will begin community outreach and schematic design in spring 2027. Spring 2027 is about when the Henry Schmidt playground is due to reopen, so Maywood's planning stage is set to begin around the time Henry Schmidt's construction finishes.
The city's May 2026 Measure I status report listed the Warburton Park playground rehabilitation as still in design, with no construction start date. Neighbors near Warburton and Maywood should start paying attention once outreach opens. Comments are easiest to act on at the schematic design stage, before a project becomes a contract with a fixed schedule.
For anyone mapping out next year in Santa Clara, the targets run in this order: Henry Schmidt's courts by Dec. 11, then in spring 2027 the Henry Schmidt playground, the Bowers lot and the start of Maywood's design, then Central Park's new entrance in summer 2027 and the International Swim Center's first phase in mid-to-late 2027. The city's park projects page is where each of those targets gets updated.
If you're getting ready to sell near one of these parks, the construction schedule is part of what buyers will ask about. A fenced playground in the listing photos tells a different story than a ribbon-cutting date a few months away. Alexandra Celo Cruz can walk you through how the timing around your street affects when to list and how to present your home. Get a Free Home Valuation & Consultation.
Stay up to date on the latest real estate trends.
Work with Alexandra for a seamless real estate experience. She helps buyers visualize dream home potential through thoughtful enhancements and guides sellers in preparing and presenting their homes to attract maximum interest and profits. With Alexandra's expertise and creative approach, your goals are within reach.